SITE UPDATE · 28 SEPTEMBER 2026 · 9:39 AM

Today’s site update: preparing for a new porcelain patio.

Protecting the property and getting the levels right before the new paving goes down.

We’ve laid floor protection to look after the property and started digging out for a new porcelain patio. The existing patio level is too high and has breached the damp-proof course, so we’re lowering the overall levels as part of the groundwork.

Floor protection in place and the start of excavation beside the house.

Getting the levels right now is an important part of building a patio that lasts. We’ll work out the finished height and drainage before laying the porcelain, taking care around the house and its damp-proof course.